Framing – Pre-Work Inspection Checklist

This checklist ensures that all necessary preparations are completed before framing begins. It focuses on verifying plans and materials, ensuring the site is clean and accessible, and confirming the foundation and structural elements are ready to support framing. By addressing these steps, the team ensures a smooth and efficient framing process with minimal disruptions or errors.

Pick up and sign for the plans

Pick up the purchase order

Receive the quantity of materials list

Clean the work area and remove all debris

Ensure the foundation is complete, square, plumb, and anchor bolts are in place

Remove all formboards from the foundation

Confirm all materials are on site and ready for use

Ensure there is adequate access for a crane

Confirm trusses are on site and ready to install

Verify that temporary electrical power is available