HVAC (Rough) – Final Inspection Checklist
This checklist ensures the HVAC system is installed correctly and meets all quality, functionality, and safety standards before the trade contractor leaves the jobsite. It focuses on the proper placement of units, secure and sealed ductwork, correct thermostat placement, and system readiness for further construction phases.
Set the heating unit(s) with necessary clearances on all sides
Ensure no ductwork is crimped, bent, or damaged to restrict airflow
Verify adequate space in the heating unit area so ductwork does not obstruct maintenance or filter changes
Ensure attic units are properly set and ducts are not crimped, bent, or damaged
Complete and properly seal all piping to the exterior of the house
Secure all ducts to boots
Seal all ducts properly at the heat exchanger
Secure all ductwork
Seal air returns and vents to the floor and place them per plan
Securely cover all floor ducts
Install all gas cutoffs properly and ensure they are accessible (e.g., for fireplaces, clothes dryers, and furnaces)
Verify thermostat locations are correct per the plan
Ensure gas pressure is adequate
Pass the rough HVAC inspection
Broom-sweep the house and remove debris
Ensure no debris is left on the lot