SOP Templates > Custom Home Construction > Trim – Pre-Work Inspection Checklist

Trim – Pre-Work Inspection Checklist

This checklist ensures the home is fully prepared for trim installation by verifying the condition of materials, surfaces, and fixtures. It focuses on cleanliness, readiness of the house and garage, and confirming that all prerequisites, such as framed doors and set cabinets, are in place. These steps ensure smooth and accurate trim installation.

Pick up and sign for the plans

Receive the purchase order

Ensure materials are on site and ready to use

Clean the house, ensuring it is broom-swept and free of debris

Clean the garage

Inspect windows to confirm they are intact and unbroken

Ensure stairs are installed

Verify drywall is undamaged

Inspect vinyl to confirm it is undamaged

Cover ducts

Cover and verify tubs are undamaged

Cover and verify sinks, cabinets, and countertops are undamaged

Confirm cabinets are set

Verify doors are framed plumb, correctly sized, and checked against plans for carpet and vinyl areas

Clearly mark the swing of each door on the inside of the doorjamb

Ensure disappearing stairs are installed, if required

Confirm attic access is framed