Construction Workflow
Welcome to the Construction Workflow SOP Template Library for New Construction (Commercial) Roofing. Access free, expertly crafted Standard Operating Procedures to guide your construction phase. Our templates cover every step, from initial setup to final installation, ensuring efficient and high-quality workmanship. Download our templates today to streamline your construction process and achieve outstanding results.
Mobilize roofing crew and set up equipment on site
Step 1: Schedule the Mobilization of Roofing Crew and Equipment
• Coordinate with the roofing crew to schedule the mobilization date and time, ensuring that all necessary equipment and materials are ready for transport
• Confirm that the site is prepared and accessible for crew and equipment setup
Step 2: Communicate Mobilization Plan to Roofing Crew
• Share the mobilization plan with the roofing crew, including specific instructions on their responsibilities, equipment setup locations, and safety protocols
• Assign a crew leader to oversee the mobilization process and address any issues
Step 3: Transport Roofing Equipment and Materials to the Site
• Arrange transportation for roofing equipment and materials to the project site, following the mobilization plan
• Verify that all items are securely loaded and properly handled during transport
Step 4: Set Up Roofing Equipment and Workstations on Site
• Upon arrival at the site, set up roofing equipment and workstations according to the site layout plan
• Ensure that all equipment is placed in designated areas for efficient workflow and safety
Step 5: Conduct an Equipment and Safety Check
• Conduct a thorough inspection of all roofing equipment to confirm that it is in good working condition and meets safety standards
• Verify that all safety measures, such as harnesses, guardrails, and fall protection systems, are in place
Step 6: Brief Roofing Crew on Site Logistics and Safety Protocols
• Brief the roofing crew on site logistics, including access points, material storage areas, and equipment locations
• Review safety protocols and emergency procedures with the crew to ensure compliance
Step 7: Document and Confirm Completion of Mobilization
• Document the completion of the mobilization process, including equipment setup, safety checks, and crew readiness
• Notify the project manager and relevant stakeholders that the crew is ready to begin work
Conduct site safety briefing with roofing crew
Step 1: Prepare a Safety Briefing Agenda and Checklist
• Prepare a detailed agenda and checklist for the safety briefing, including key topics such as site hazards, safety protocols, and emergency procedures
• Include specific items relevant to roofing activities, such as fall protection and weather-related risks
Step 2: Gather All Roofing Crew Members for the Safety Briefing
• Gather all roofing crew members at a designated meeting location on-site for the safety briefing
• Confirm that all crew members are present and ready to participate in the briefing
Step 3: Review Site Hazards and Specific Roofing Safety Measures
• Review any identified site hazards with the crew, such as unprotected edges, overhead power lines, or weather-related risks
• Discuss specific safety measures for roofing tasks, such as the proper use of harnesses, ladders, and scaffolding
Step 4: Explain Fall Protection and Personal Protective Equipment (PPE) Requirements
• Explain the requirements for fall protection equipment, such as harnesses, guardrails, and safety nets
• Ensure that all crew members understand the proper use and inspection of PPE, including helmets, gloves, and high-visibility vests
Step 5: Establish Emergency Procedures and Communication Protocols
• Establish emergency procedures for incidents such as falls, accidents, or severe weather conditions
• Confirm the communication protocols for reporting emergencies and contacting on-site safety personnel
Step 6: Encourage Crew Members to Ask Questions and Share Concerns
• Encourage crew members to ask questions or raise concerns about site safety and protocols
• Address any issues or provide additional guidance as needed
Step 7: Document Attendance and Key Takeaways from the Safety Briefing
• Document the attendance of all crew members at the safety briefing, along with key takeaways and any identified concerns
• Save a copy of the briefing notes in the project records for future reference
Coordinate with general contractor (GC) and other subcontractors on site
Step 1: Schedule Daily or Weekly Coordination Meetings with GC
• Schedule regular coordination meetings with the General Contractor (GC) to review project progress, address site issues, and discuss upcoming tasks
• Confirm the meeting schedule and key discussion points with the GC and subcontractors
Step 2: Establish Clear Communication Channels with All Subcontractors
• Set up communication channels for all subcontractors, including designated points of contact and preferred methods of communication
• Share the contact list and communication protocols with the project team and subcontractors
Step 3: Review and Align Work Schedules and Task Dependencies
• Review and align work schedules with the GC and other subcontractors to avoid conflicts and ensure smooth workflow
• Identify key dependencies between tasks and adjust schedules as needed to prevent delays
Step 4: Coordinate Site Access, Equipment Usage, and Safety Protocols
• Coordinate site access points, equipment usage, and safety protocols to prevent congestion and ensure safe operations
• Confirm that all subcontractors are aware of site logistics, equipment schedules, and safety guidelines
Step 5: Address Any Conflicts or Issues on Site Promptly
• Monitor daily activities to identify any conflicts or issues that arise between subcontractors
• Work with the GC to resolve conflicts quickly and maintain progress on the project
Step 6: Document Key Decisions and Changes in the Project Plan
• Document key decisions, schedule changes, and any adjustments made during coordination meetings
• Update the project plan and communicate changes to all relevant team members
Step 7: Regularly Review Progress and Provide Updates to Stakeholders
• Regularly review the project’s progress with the GC and subcontractors to ensure alignment with the overall schedule
• Provide updates to key stakeholders, including the project manager and client, as needed
Verify delivery and inventory of roofing materials
Step 1: Review and Confirm Delivery Schedule with Suppliers
• Review the delivery schedule with suppliers to confirm the dates, times, and quantities of roofing materials expected on-site
• Verify any special handling or storage requirements for specific materials
Step 2: Prepare a Material Checklist for Inventory Verification
• Prepare a detailed checklist of all roofing materials to be delivered, including quantities, specifications, and order numbers
• Ensure that the checklist matches the purchase orders and supplier invoices
Step 3: Inspect Roofing Material Deliveries Upon Arrival
• Inspect each delivery of roofing materials upon arrival to confirm that all items match the order specifications and quantities
• Check for any visible damage, defects, or missing items during the inspection
Step 4: Document and Report Any Discrepancies or Damages
• Document any discrepancies or damaged materials in the delivery records and notify the supplier immediately
• Work with the supplier to arrange for replacement or additional deliveries if needed
Step 5: Organize and Store Roofing Materials on Site
• Organize and store the roofing materials in designated areas to prevent damage and ensure easy access for installation
• Label and secure all materials according to the site logistics plan
Step 6: Verify and Update Material Inventory Records
• Update the material inventory records to reflect the delivered quantities and any adjustments made
• Keep digital and physical copies of delivery receipts and inventory logs for reference
Step 7: Communicate Material Availability to Project Team
• Inform the project team of the material delivery status and availability for installation
• Highlight any issues or delays that could impact the project timeline
Prepare roof deck for installation (e.g., clean, inspect)
Step 1: Conduct a Visual Inspection of the Roof Deck
• Conduct a visual inspection of the roof deck to check for any damage, debris, or moisture that could affect the roofing installation
• Look for signs of rot, cracks, or structural weaknesses that need to be addressed
Step 2: Clean the Roof Deck Thoroughly
• Remove any debris, dirt, or loose materials from the roof deck to create a clean and stable surface for installation
• Use brooms, blowers, or vacuums as needed to achieve a clean deck
Step 3: Repair Any Identified Damage or Weaknesses
• Make any necessary repairs to the roof deck, such as replacing damaged plywood or reinforcing weak areas
• Ensure that all repairs are completed and inspected before proceeding with the next steps
Step 4: Install Roof Decking or Sheathing if Required
• If new roof decking or sheathing is needed, install the appropriate materials according to the project specifications
• Verify that the installed decking meets the necessary building codes and standards
Step 5: Check for Proper Roof Slope and Ventilation
• Verify that the roof deck has the proper slope and ventilation according to the project plans and building codes
• Make any adjustments needed to ensure proper drainage and airflow
Step 6: Document the Condition of the Roof Deck
• Document the condition of the roof deck after cleaning and repairs, including photos and inspection notes
• Save the documentation in the project records for reference during installation
Step 7: Communicate Roof Deck Readiness to Roofing Crew
• Communicate the readiness of the roof deck to the roofing crew and project manager, confirming that it is prepared for the next phase of installation
Install roofing underlayment and moisture barrier
Step 1: Select and Prepare the Appropriate Underlayment Materials
• Select the appropriate roofing underlayment and moisture barrier materials based on the project specifications and climate conditions
• Verify that all materials are in good condition and meet the required standards
Step 2: Lay the Roofing Underlayment Over the Roof Deck
• Begin laying the roofing underlayment over the clean and inspected roof deck, starting from the eaves and working up toward the ridge
• Ensure that the underlayment is installed smoothly and securely, avoiding wrinkles or gaps
Step 3: Overlap and Secure the Underlayment Properly
• Overlap each row of underlayment according to the manufacturer’s guidelines, typically 3 to 6 inches
• Secure the underlayment with appropriate fasteners, such as roofing nails or staples, following building code requirements
Step 4: Install the Moisture Barrier in Key Areas
• Install the moisture barrier in key areas such as valleys, roof penetrations, chimneys, and eaves
• Use adhesive or fasteners to secure the moisture barrier tightly in place, preventing water infiltration
Step 5: Inspect the Installed Underlayment for Coverage and Quality
• Inspect the installed underlayment to confirm full coverage and quality of installation
• Check that all edges are properly sealed and that there are no exposed areas or vulnerabilities
Step 6: Address Any Gaps or Defects in the Underlayment
• Address any gaps, tears, or defects in the underlayment by applying additional layers or patches as needed
• Verify that all corrections are properly secured and meet project specifications
Step 7: Document the Installation of the Underlayment and Moisture Barrier
• Document the installation of the underlayment and moisture barrier with photos and notes for quality assurance
• Save the documentation in the project records for future reference
Install roofing materials (e.g., shingles, tiles, metal panels)
Step 1: Prepare Roofing Materials for Installation
• Prepare the roofing materials, such as shingles, tiles, or metal panels, by organizing and staging them in designated areas on-site
• Confirm that all materials are clean, dry, and free of defects before installation
Step 2: Begin Installation from the Roof’s Edge or Starter Row
• Begin installing the roofing materials from the roof’s edge or starter row, following the manufacturer’s installation guidelines
• Align the first row carefully to ensure a straight and even starting point for the rest of the installation
Step 3: Secure Roofing Materials According to Manufacturer’s Guidelines
• Secure the roofing materials using the recommended fasteners and spacing guidelines provided by the manufacturer
• Confirm that all fasteners are properly driven in and that materials are tightly secured to the roof deck
Step 4: Maintain Consistent Alignment and Overlapping of Materials
• Maintain consistent alignment and overlapping of roofing materials to prevent gaps and ensure a professional appearance
• Regularly check the alignment with a measuring tape or chalk line as installation progresses
Step 5: Install Flashing and Seal All Roof Penetrations
• Install flashing around roof penetrations, such as chimneys, vents, and skylights, to prevent water infiltration
• Use appropriate sealants and flashing materials to ensure a watertight seal
Step 6: Inspect Installed Roofing for Quality and Compliance
• Inspect the installed roofing materials to verify that they meet project specifications and quality standards
• Address any issues such as misaligned rows, loose fasteners, or exposed edges
Step 7: Document and Communicate Completion of Roofing Installation
• Document the completion of the roofing installation with photos and inspection notes
• Communicate the completion status to the project manager and key stakeholders for approval
Install flashing and other roof penetrations
Step 1: Review Project Plans for Flashing and Roof Penetrations
• Review the project plans and specifications to identify all areas requiring flashing and roof penetrations
• Confirm the required types and materials for flashing around each penetration, such as chimneys, vents, and skylights
Step 2: Prepare Flashing Materials for Installation
• Measure and cut flashing materials to the correct size and shape, ensuring proper coverage of the roof penetrations
• Use appropriate tools to achieve clean and precise edges on all flashing pieces
Step 3: Install Flashing in Key Penetration Areas
• Secure flashing around each penetration, ensuring it overlaps with the roofing materials to create a watertight seal
• Apply the flashing tightly against the roof surface, avoiding gaps or wrinkles
Step 4: Seal and Fasten Flashing Properly
• Use manufacturer-recommended sealants and fasteners to secure the flashing in place
• Ensure that fasteners are properly driven and sealant is evenly applied to prevent water infiltration
Step 5: Inspect Flashing Installation for Completeness and Quality
• Inspect the installed flashing to confirm full coverage, proper alignment, and secure fastening
• Look for any gaps, exposed edges, or loose sections that require adjustments
Step 6: Apply Additional Protective Measures If Needed
• If required by project specifications, apply additional protective measures like waterproof membranes or underlayment strips around critical penetrations
• Secure these layers properly to maintain a watertight seal
Step 7: Document Completion of Flashing Installation
• Take photos and notes to document the completion of flashing and roof penetrations
• Communicate completion status to the project manager and relevant stakeholders
Conduct weekly quality control inspections
Step 1: Schedule Regular Quality Control Inspections
• Establish a regular schedule for weekly quality control inspections with the project team
• Confirm the inspection dates, times, and roles of key team members involved in the inspection process
Step 2: Prepare a Comprehensive Quality Control Checklist
• Develop a detailed checklist covering key quality aspects of the roofing work, such as material installation, flashing, and adherence to specifications
• Include criteria for workmanship, safety compliance, and regulatory standards
Step 3: Conduct Visual and Hands-On Inspections
• Conduct both visual and hands-on inspections of the roofing work, focusing on key elements like underlayment, flashing, and roof penetrations
• Verify that all installed components meet the project’s specifications and quality standards
Step 4: Identify and Document Issues and Non-Compliance Areas
• Identify and document any issues or areas that do not comply with the project specifications or quality standards
• Take photos and detailed notes to describe each issue, including the location and severity
Step 5: Communicate Inspection Findings to the Project Team
• Communicate the results of the quality control inspection to the project team and relevant stakeholders
• Highlight any critical issues that require immediate corrective actions and assign responsibilities
Step 6: Track and Monitor Corrective Actions
• Establish a process to track and monitor corrective actions taken to address identified issues
• Schedule follow-up inspections to confirm that all corrective actions have been successfully completed
Step 7: Maintain Quality Control Records and Reports
• Save all quality control inspection reports, photos, and follow-up notes in the project records
• Regularly review these records to ensure continuous improvement in project quality
Coordinate with GC for periodic inspections
Step 1: Establish an Inspection Schedule with the GC
• Establish a schedule for periodic inspections with the General Contractor (GC) that aligns with key project milestones and critical phases
• Confirm inspection dates, times, and areas of focus with the GC and other relevant stakeholders
Step 2: Prepare Inspection Agendas and Documentation
• Prepare agendas for each inspection, outlining key points for discussion and specific areas to be inspected
• Gather necessary documents, such as project plans, specifications, and past inspection reports, for reference during inspections
Step 3: Notify Project Team and Subcontractors of Inspection Schedule
• Communicate the inspection schedule to the project team and all subcontractors, ensuring that all involved parties are aware of the upcoming inspections
• Confirm that all areas to be inspected are accessible and ready
Step 4: Participate in Joint Inspections with GC and Key Stakeholders
• Participate in joint inspections with the GC, client representatives, and key subcontractors
• Conduct a thorough walkthrough of the designated areas, noting compliance with project specifications and quality standards
Step 5: Document Inspection Findings and Decisions
• Document all findings and decisions made during the inspections, including any corrective actions required
• Take photos and detailed notes to ensure accurate record-keeping
Step 6: Follow Up on Agreed-Upon Actions from Inspections
• Follow up with the GC and subcontractors on any corrective actions or adjustments required based on the inspection findings
• Schedule follow-up inspections as needed to verify that issues have been resolved
Step 7: Update Project Records with Inspection Reports and Outcomes
• Update the project records with completed inspection reports, photos, and documentation of any agreed changes or actions taken
• Communicate key outcomes to the project team and stakeholders
Perform site cleanup and waste disposal of roofing materials
Step 1: Establish a Waste Management Plan for Roofing Activities
• Develop a waste management plan that outlines procedures for handling and disposing of roofing materials, including debris, packaging, and unused materials
• Identify designated disposal areas and recycling points on-site
Step 2: Assign Responsibilities for Site Cleanup
• Assign specific team members or subcontractors to be responsible for site cleanup and waste disposal activities
• Communicate these responsibilities clearly to all crew members during daily briefings
Step 3: Collect and Segregate Roofing Debris and Waste Materials
• Collect all roofing debris and waste materials from the work area, ensuring they are properly segregated based on disposal or recycling requirements
• Use designated bins or containers to keep different types of waste organized
Step 4: Dispose of Waste Materials According to Regulations
• Dispose of waste materials in compliance with local regulations and environmental guidelines
• Ensure that hazardous materials, such as chemicals or adhesives, are handled and disposed of according to safety standards
Step 5: Conduct a Final Walkthrough to Verify Site Cleanliness
• Conduct a final walkthrough of the work area to verify that all waste materials have been removed and the site is clean and safe
• Address any remaining debris or clutter that could pose a hazard or affect project quality
Step 6: Document and Report the Completion of Site Cleanup
• Document the completion of the site cleanup with photos and notes, indicating the status of waste disposal
• Report the completion to the project manager and update the project records
Step 7: Communicate Site Cleanup Requirements to Crew Members
• Remind crew members of the ongoing site cleanup requirements and the importance of maintaining a clean and organized work area
• Reinforce waste management practices during daily safety briefings
Conduct final inspection of the roofing work
Step 1: Schedule the Final Roofing Inspection with Key Stakeholders
• Schedule the final roofing inspection with key stakeholders, including the project manager, GC, client representatives, and any relevant subcontractors
• Confirm the inspection date, time, and areas of focus with all participants
Step 2: Prepare a Final Inspection Checklist Based on Project Specifications
• Develop a comprehensive final inspection checklist based on the project specifications, ensuring that all key aspects of the roofing work are covered
• Include criteria for material quality, installation accuracy, and compliance with safety standards
Step 3: Conduct a Thorough Walkthrough and Inspection of Roofing Work
• Conduct a thorough walkthrough of the roofing work, focusing on critical areas such as roofing materials, flashing, roof penetrations, and moisture barriers
• Use the final inspection checklist to systematically review each component of the roofing work
Step 4: Verify Compliance with Project Specifications and Standards
• Verify that all roofing work complies with the approved project specifications, manufacturer guidelines, and local building codes
• Pay special attention to areas requiring precise workmanship, such as valleys, eaves, and ridges
Step 5: Document Any Outstanding Issues or Deficiencies
• Document any outstanding issues or deficiencies identified during the final inspection, including photos and detailed notes
• Discuss each issue with the project team and assign corrective actions as needed
Step 6: Confirm Completion of Corrective Actions
• Once corrective actions are completed, schedule a follow-up inspection to verify that all issues have been resolved and the roofing work meets quality standards
• Update the project records with the final inspection results
Step 7: Obtain Client Approval and Sign-Off on Roofing Work
• Present the final inspection results to the client for their review and approval
• Obtain the client’s sign-off on the completed roofing work and document the approval in the project records
Notify GC that roofing work is substantially complete
Step 1: Review Roofing Work to Confirm Substantial Completion
• Conduct a thorough review of the completed roofing work to verify that all key tasks are substantially complete and align with project specifications
• Ensure that all major roofing components, such as shingles, flashing, and moisture barriers, are properly installed
Step 2: Prepare a Substantial Completion Report for Roofing Work
• Prepare a substantial completion report that outlines the status of the roofing work, highlighting completed areas and any minor outstanding tasks
• Include photos and notes to support the report’s findings
Step 3: Notify GC of Roofing Work Completion via Formal Communication
• Send a formal notification to the General Contractor (GC) informing them that the roofing work is substantially complete
• Include the substantial completion report in the communication to provide a detailed overview
Step 4: Offer to Schedule a Preliminary Inspection with the GC
• Offer to schedule a preliminary inspection with the GC to review the completed roofing work and address any immediate questions or concerns
• Confirm the availability of key team members for the inspection
Step 5: Document and Save All Completion Notifications and Reports
• Save copies of all communications and reports related to the substantial completion notification in the project records
• Ensure that the project manager and key stakeholders are aware of the completion status
Step 6: Prepare to Address Any Feedback from the GC
• Be prepared to address any feedback or requests for additional information from the GC regarding the substantial completion of the roofing work
• Assign responsibilities to the project team for handling follow-up actions as needed
Step 7: Communicate Substantial Completion Status to Roofing Crew
• Communicate the substantial completion status to the roofing crew, highlighting any remaining minor tasks or touch-ups that need to be completed
Construction SOPs Your Employees Will Actually Use!
Subtrak’s game-changing SOP software helps contractors effortlessly document their processes and automatically delegate tasks to their entire project team, making sure everyone knows exactly what to do and when.
Schedule a demo today to see how Subtrak can save you time, money, and headaches!
Download Our Free eBook
Get Blueprint for Success, our free guide to scaling and systemizing your specialty trade construction business.